ARTVİN / DEREİÇİ
Artvin / Dereiçi Project
The project is located within the borders of the province of Artvin at a distance of 66 km to the city. The geology of the license area of 1.680 hectares consists of volcanic-sediment geologic sequences. In the prospecting site, massive sulphide & porphyry type Cu-Pb-Zn and Au-Ag mineralization is observed widely.
A total of 27.142 meters (at 121 diamond drill holes) of core drilling has been completed in the license area. In terms of geophysical works, a total of 120.900 m IP/RES has been measured on 58 lines by the Pole-Dipole method whereas a total of 88.670 meters of magnetic measures have been taken on 43 lines.
To determine the distribution of Cu Zn Pb Mo Au Ag mineralized zones, 4352 laboratory analysis results were evaluated. Preliminary ore modeling/resource estimate and metallurgical testworks have been completed. Detail exploration field studies for resource enhancement in license area are in progress.
ORDU / ÇAMAŞ
Ordu / Çamaş Mining Project
The project is located within the borders of the province of Ordu at a distance of 31 km to the city. The geology of four adjacent license areas of total 4.718 hectares consists of volcanic-sediment sequences. In the prospecting site, multiple vein type sulphide Cu-Pb-Zn and Au-Ag mineralization is observed extensively.
The Harput Mining Company, which was founded as a Sadioğulları Mining Company, started mining operations in 2013. The mining licensing status of the Ordu Project is consist of 4 adjacent licenses which are three in detail status and one in operation status, total area of 6245 hectares.
A total of 12.343 meters (at 52 diamond drill holes) of core drilling has been completed in the license area. In terms of geophysical works, a total of 24.850 meters IP/RES works have been conducted on 22 lines by Pole-Dipole method.
To determine the distribution of Pb Zn Cu & Au Ag mineralized zones, 3041 laboratory analysis results were evaluated. With present licenses, general geologic mapping have been completed. Resource enhancement studies are continuing. Preliminary ore modeling/resource estimate and metallurgical tests of the area have been accomplished. Detail works for resource enhancement in license area are in progress.